Metro Central Bay 2 SOG Replacement

Client: Metro 

Architect:  Metro

City: Portland, OR
Value: $525 K
Size: 24,000 sq ft

 

Project consisted of a fast tracked, 10-day shutdown of Bay 2 to remove approx. 24,000 SF of failing concrete SOG, reserving trucking services to provide an unknown quantity of aggregate backfill once the existing concrete SOG was removed, to achieve grade, prior to pouring a new 12” reinforced SOG. Concrete work was phased into two separate pours to allow for operations to immediately resume within 7-days of the initial pour.